When the Connecticut Siting Council granted a certificate of environmental compatibility and public need approving the Cross-Sound cable in January 2002, it determined that the project would provide a public benefit and would not have an environmental impact constituting “sufficient reason to deny the application.” The 330-MW transmission cable was installed beneath the seabed of Long Island Sound between Connecticut and New York in the spring of 2002, months after the state siting and environmental permits, and a federal dredging permit were granted for this electric transmission line project.